Kathy Sullivan: A busy 2019 summer | Columnists | unionleader.com
ALTHOUGH SUMMER generally is a slow time in New Hampshire politics, much is happening in this summer of 2019. Here are a few newsworthy topics.
UnionLeader  column  northernpass  supremecourt  appeal  SEC  opponent 
20 days ago by eversourcenh
Eversource gives up on Northern Pass project after spending $318 million | Business | unionleader.com
Eversource has given up on its proposed $1.6 billion Northern Pass transmission-line power project after spending $318 million on land and other project costs.
UnionLeader  northernpass  supremecourt  appeal  SEC 
23 days ago by eversourcenh
Eversource gives up on Northern Pass hydropower project
Bowing to the inevitable, Eversource has officially taken Northern Pass off the table.
concordmonitor  northernpass  supremecourt  appeal  SEC 
23 days ago by eversourcenh
Power Line Requiem or the Northern Pass Megawatt Blues - InDepthNH.orgInDepthNH.org
The playing field changed in the decade the Northern Pass Transmission Project was before the public with its end coming “not with a bang but a whimper.”
InDepthNH  northernpass  supremecourt  appeal  SEC 
23 days ago by eversourcenh
Eversource gives up on Northern Pass hydropower project - The Washington Post
After nearly a decade of protests, hearings and court fights, the Northern Pass hydropower project that promised to bring hydropower from Canada to southern New England is dead.
washingtonpost  ap  northernpass  supremecourt  appeal  SEC 
23 days ago by eversourcenh
Eversource Drops Plan to Build Northern Pass Line in New Hampshire
Eversource Energy said it no longer plans to construct the Northern Pass transmission line in New Hampshire after the state’s Supreme Court upheld regulators’ decision rejecting the siting permit.
bloomberg  northernpass  supremecourt  appeal  SEC 
23 days ago by eversourcenh
With $318M Invested, Eversource Pulls Plug on Northern Pass
Appellate defeat brought about the end Thursday of the Northern Pass, a $1.6 billion hydropower project that would have run 192 miles through New Hampshire into Canada.
courthousenewsservice  northernpass  supremecourt  sec  filing 
25 days ago by eversourcenh
Site Evaluators Reject Appeal Of Seacoast Power Line Approval | New Hampshire Public Radio
The state’s Site Evaluation Committee says it won’t reconsider its recent approval of a new transmission line on the Seacoast.
nhpr  SRP  sec  appeal  decision 
april 2019 by eversourcenh
SEC won't reconsider Seacoast Reliability Project - News - seacoastonline.com - Portsmouth, NH
On Thursday, state regulators denied motions to rehear and reconsider their approval of the Seacoast Reliability Project that the town of Durham, the Durham residents group and the Conservation Law Foundation filed in March.
seacoastonline  InDepthNH  SRP  sec  rehearing  decision 
april 2019 by eversourcenh
Eversource objects to regulators rehearing Seacoast powerline project
Eversource objected Friday to motions for rehearing the Seacoast Reliability Project filed Monday by the town of Durham, Conservation Law Foundation and Durham residents.
seacoastonline  SRP  sec  rehearing 
march 2019 by eversourcenh
Great Bay Advocates Appeal N.H. SEC Approval Of Eversource Power Line | New Hampshire Public Radio
The New Hampshire Site Evaluation Committee will decide next week whether to reconsider its approval of a new power line on the Seacoast.
nhpr  SRP  sec  appeal 
march 2019 by eversourcenh
Groups Seek Rehearing of Unpopular Seacoast Reliability Project Approval - InDepthNH.orgInDepthNH.org
The Conservation Law Foundation, town of Durham and a group of Durham residents have asked state regulators to reconsider their decision to grant Eversource a certificate to build an unpopular 13-mile transmission line from Madbury to Portsmouth.
InDepthNH  SRP  sec  rehearing 
march 2019 by eversourcenh
Opponents of Seacoast transmission line project don't rule out court fight | Energy | unionleader.com
Opponents of a state-approved $84 million transmission-line project designed to boost the reliability of the region’s electric system haven’t ruled out going to court to overturn its approval.
UnionLeader  SRP  sec  decision 
february 2019 by eversourcenh
Seacoast Reliability Project gets final approval
The state’s Site Evaluation Committee has released its written order approving the Seacoast Reliability Project for Eversource to build an unpopular 13-mile transmission line from Madbury to Portsmouth.
seacoastonline  positive  SRP  sec  decision 
february 2019 by eversourcenh
SEC Releases Seacoast Reliability Project's Final Order With Conditions - InDepthNH.orgInDepthNH.org
The Site Evaluation Committee has released its final written order approving the Seacoast Reliability Project for Eversource to build an unpopular 13-mile transmission line from Madbury to Portsmouth.
InDepthNH  positive  SRP  sec  decision 
february 2019 by eversourcenh
Eversource issues Statement on NH Site Evaluation Committee’s Written Order Approving the Seacoast Reliability Project – Londonderry News
Eversource released the following statement after the New Hampshire Site Evaluation Committee issued its written order approving the Seacoast Reliability Project:
londonderrynews  positive  SRP  sec  decision 
february 2019 by eversourcenh
Top ten 2018 stories: Battles over energy, police reform, education choice and more | News | unionleader.com
In March the New Hampshire Site Evaluation Committee issued its formal written decision that denied Eversource’s bid for the controversial Northern Pass transmission line.
UnionLeader  northernpass  sec  decision 
december 2018 by eversourcenh
Top 10 2018 business stories: Amazon, internet sales tax, power projects top the list | Business | unionleader.com
State regulators on Feb. 1 unanimously rejected the $1.6 billion Northern Pass electric transmission project. Critics complained about the tall proposed power towers and environmental fallout they predicted along parts of the proposed 192-mile route. Eversource said its project would bring hydropower from Canada into New England.
UnionLeader  northernpass  sec  decision 
december 2018 by eversourcenh
2018 Stories of the Year: Northern Pass died – but the debate didn’t
In 2018 Northern Pass failed, except that it didn’t quite die and even if it did, a whole bunch of related arguments are going to continue for a long, long time.
concordmonitor  northernpass  sec  decision 
december 2018 by eversourcenh
Top stories 2018 | No. 6: Infrastructure investments reshape region
Earlier this month, New Hampshire’s Site Evaluation Committee unanimously approved Eversource’s application to build a new, 13-mile, 115kv high-voltage transmission line between substations in Madbury and Portsmouth, with one mile of the line buried beneath Little Bay. Eversource successfully argued the $84 million infrastructure upgrade is necessary to meet the growing energy demands of the Seacoast, which would be paid by all electric consumers in New England. The company has said without the project, rolling blackouts could be possible.
seacoastonline  SRP  sec  approval 
december 2018 by eversourcenh
Second Sununu choice for SEC pulls out | State | unionleader.com
Gov. Chris Sununu lost the second of his three picks to join the state Site Evaluation Committee with former Republican state Rep. Michael Vose of Epping withdrawing his nomination Tuesday on the eve of a showdown vote on the Executive Council.
UnionLeader  sununu  sec  appointment  vose 
december 2018 by eversourcenh
Sununu’s Latest Site Evaluation Committee Nominee Drops Out | New Hampshire Public Radio
Governor Chris Sununu's latest nominee to the state Site Evaluation Committee has withdrawn from consideration.
nhpr  sununu  sec  appointment  vose 
december 2018 by eversourcenh
Day before a doomed vote, Sununu’s pick to sit on SEC withdraws
Gov. Chris Sununu’s nominee to the state’s powerful Site Evaluation Committee – a former Republican state representative and supporter of the controversial Northern Pass energy transmission line project – withdrew from consideration Tuesday.
concordmonitor  sununu  sec  appointment  vose 
december 2018 by eversourcenh
Dolly McPhaul: Sununu must choose between the people and Eversource
It is time for Gov. Chris Sununu to place his allegiance with the people of New Hampshire, where it belongs.
concordmonitor  op-ed  sununu  sec  northernpass  opponent 
december 2018 by eversourcenh
Letter: Vose doesn’t belong on Site Evaluation Committee
Gov. Chris Sununu has nominated Michael Vose to the New Hampshire Site Evaluation Committee, which has the power to review the siting of new energy projects.
concordmonitor  letter  sununu  sec  northernpass  opponent 
december 2018 by eversourcenh
Site Evaluators Approve Eversource's Seacoast Power Line | New Hampshire Public Radio
The state Site Evaluation Committee has given Eversource the green light to build a new transmission line on the Seacoast.
nhpr  positive  SRP  sec  approval 
december 2018 by eversourcenh
'Moment of Truth,' Regulators Approve Seacoast Reliability Project Amid Citizen Concerns - InDepthNH.orgInDepthNH.org
To the dismay of some local residents, the Site Evaluation Committee unanimously approved the $84 million, 13-mile Seacoast Reliability Project from Madbury to Portsmouth on Monday.
InDepthNH  positive  SRP  sec  approval 
december 2018 by eversourcenh
State regulators approve $84M transmission line project | Environment | unionleader.com
State regulators on Monday unanimously approved a proposed $84 million transmission-line project designed to boost the reliability of the region’s electric system.
UnionLeader  positive  SRP  sec  approval 
december 2018 by eversourcenh
SEC: Citizens, Businesses Must Pay Part of Mediation In Seacoast Project - InDepthNH.orgInDepthNH.org
The Site Evaluation Committee deliberated Friday on whether the Seacoast Reliability Project would have an unreasonable impact on orderly development of the region, the same criteria required for project approval that scuttled Northern Pass in February.
InDepthNH  SRP  sec  finaldeliberations 
december 2018 by eversourcenh
SEC's Deliberations Moving Quickly on Seacoast Reliability Project - InDepthNH.orgInDepthNH.org
The Site Evaluation Committee that will decide whether Eversource can build the Seacoast Reliability Project decided Thursday that it wouldn’t have an unreasonable impact on flora and fauna of Little Bay or along the 13-mile proposed high-voltage line from Madbury to Portsmouth.
InDepthNH  SRP  sec  finaldeliberations 
december 2018 by eversourcenh
Seacoast Reliability Project continues to clear hurdles
The Site Evaluation Committee that will decide whether Eversource can build the Seacoast Reliability Project decided Thursday that it wouldn’t have an unreasonable impact on flora and fauna of Little Bay or along the 13-mile proposed high-voltage line from Madbury to Portsmouth.
fosters  SRP  sec  finaldeliberations 
december 2018 by eversourcenh
Testimony Shows Public Trust an Issue in Seacoast Reliability Project - InDepthNH.orgInDepthNH.org
As regulators deliberate the fate of the $84 million Seacoast Reliability Project, concerns have been raised about the level of trust between its developer Eversource and property owners along the 13-mile proposed route from Madbury to Portsmouth.
InDepthNH  SRP  sec  finaldeliberations 
december 2018 by eversourcenh
Day 3: Burying Cable Beneath Little Bay Focus of Seacoast Project Deliberations - InDepthNH.orgInDepthNH.org
Day three of deliberations on the proposed 13-mile high-voltage powerline from Madbury to Portsmouth likely dashed some intervenors’ hope that developer Eversource would use another method instead of jet plowing to bury the one-mile portion underneath Little Bay.
InDepthNH  SRP  sec  finaldeliberations 
december 2018 by eversourcenh
Deliberations Begin in Concord on $84M Seacoast Reliability Project - InDepthNH.orgInDepthNH.org
After 17 adjudicative hearings, state regulators began Wednesday deliberating the fate of the Seacoast Reliability Project – a 13-mile, $84 million high-voltage transmission line proposed to run from Madbury to Portsmouth.
InDepthNH  SRP  sec  finaldeliberations 
november 2018 by eversourcenh
Final Deliberations Begin For Eversource’s Seacoast Power Line | New Hampshire Public Radio
State regulators will begin final deliberations Wednesday on a proposed Seacoast transmission line.
nhpr  SRP  sec  finaldeliberations 
november 2018 by eversourcenh
Seacoast Reliability Project ruling looms
This week begins the final leg of Eversource’s application process to build a 13-mile high-voltage transmission line between substations in Madbury and Portsmouth it dubbed the Seacoast Reliability Project.
fosters  SRP  sec  finaldeliberations 
november 2018 by eversourcenh
Eversource Seeks To Reopen Record on Seacoast Reliability Project - InDepthNH.orgInDepthNH.org
Eversource wants to reopen the record on the 12.9-mile high-voltage transmission line – or Seacoast Reliability Project – to provide information on potentially impacted historic and scenic resources.
InDepthNH  SRP  sec 
november 2018 by eversourcenh
Seacoast Reliability Project decision expected by early December - News - seacoastonline.com - Portsmouth, NH
Whether Eversource will be approved to build a 12.9-mile high-voltage transmission line that traverses mostly through Durham and Newington could be decided before the beginning of December.
seacoastonline  SRP  sec  publichearings 
october 2018 by eversourcenh
Northern Pass Opponents Ask Supreme Court To Dismiss Appeal, Uphold Rejection | New Hampshire Public Radio
Several groups are asking the state Supreme Court to uphold regulators' denial of the Northern Pass project.
nhpr  positive  northernpass  sec  supremecourt  appeal  intervener  opponents  spnhf 
august 2018 by eversourcenh
Northern Pass Opponents To Ask Supreme Court to Affirm SEC Decision - InDepthNH.orgInDepthNH.org
The Society for the Protection of New Hampshire Forests, in concert with other stakeholders opposed to Northern Pass, will file a motion asking the New Hampshire Supreme Court to affirm the decision to deny a permit to Northern Pass and reject the appeal submitted earlier this month by Eversource.
InDepthNH  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
N.H. Regulators Begin Hearings on Eversource's Proposed Seacoast 'Reliability Project' | New Hampshire Public Radio
Hearings began Wednesday on Eversource’s proposed transmission line between Madbury to Portsmouth.
nhpr  positive  SRP  sec  hearing 
august 2018 by eversourcenh
Final Hearings Set To Begin On Eversource's Seacoast Power Line | New Hampshire Public Radio
Final hearings are scheduled to start this week on Eversource's proposed Seacoast transmission line – but delays at the state Site Evaluation Committee are still possible.
nhpr  SRP  sec  hearing 
august 2018 by eversourcenh
Opinion: Northern Pass Appeal Ignores Wishes of NH People - InDepthNH.orgInDepthNH.org
Eversource recently appealed to New Hampshire’s Supreme Court, contesting the Site Evaluation Committee’s (SEC) denial of Northern Pass. This appeal was expected by those in the NH community rights movement because when corporations don’t get the answers they want, they challenge the decision-making system, with only required consideration for the wishes of people affected by a proposed project.
InDepthNH  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Sides square off on Seacoast transmission-line plan | New Hampshire
A proposed $84 million transmission-line project that would be buried partly in Little Bay pits a need for more capacity to transmit power through the region versus concerns over disrupting the bay.
UnionLeader  positive  SRP  sec  hearing 
august 2018 by eversourcenh
Northern Pass appeals state siting decision to NH Supreme Court
Northern Pass Transmission, LLC (NPT) filed an appeal to the NH Supreme Court last week challenging a recent decision by the New Hampshire Site Evaluation Committee (SEC) denying a permit to build the proposed clean energy project.
Cooscountydemocrat  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Northern Pass Appeals Siting Decision to New Hampshire Supreme Court
The next phase of the battle over the Northern Pass transmission line project will be fought at the N.H. Supreme Court, to which Eversource filed an appeal on Friday.
colebrooknewsandsentinel  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Northern Pass appeals state siting decision to N.H. Supreme Court | News | eagletimes.com
Northern Pass Transmission, LLC (NPT) has filed an appeal to the New Hampshire Supreme Court challenging a recent decision by the New Hampshire Site Evaluation Committee (SEC) denying a permit to build the proposed clean energy project.
EagleTimes  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Northern Pass Appeals State Siting Decision to NH Supreme Court
Northern Pass Transmission, LLC last week filed an appeal to the NH Supreme Court challenging a recent decision by the NH Site Evaluation Committee (SEC) denying a permit to build the proposed clean energy project. Northern Pass proponents believe that a favorable court ruling will enable the project to return to the SEC for further review in 2019.
T&Dworld  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Northern Pass asks court to force reconsideration of transmission project | New Hampshire
Northern Pass submitted an appeal to the state Supreme Court on Friday in an effort to force a state committee to reconsider its rejection of the proposed $1.6 billion hydroelectric transmission line.
UnionLeader  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Eversource Files Northern Pass Appeal, Asks Supreme Court to Overturn SEC Ruling | New Hampshire Public Radio
Eversource has filed an appeal with the New Hampshire Supreme Court, asking them to overturn the rejection of the Northern Pass power line proposal. The filing queues up the next phase of the years-long battle over the project. (Read the full appeal text below.)
nhpr  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Northern Pass Appeals Saying 'Vague' Criteria Used To Deny Project - InDepthNH.orgInDepthNH.org
The criteria the Site Evaluation Committee used to deny the Northern Pass Transmission project was “unduly or impermissibly vague,” developer Eversource claims in appealing the decision to the state Supreme Court.
InDepthNH  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
High court to decide fate of Eversource transmission line | masslive.com
As southern New England pushes to import more hydropwer from Canada, energy developers are jostling for the right to build major transmission lines across the north.
MassLive  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Eversource appeals Northern Pass case to N.H. top court | Boston Herald
Eversource has appealed the rejection of its Northern Pass transmission line proposal to the New Hampshire Supreme Court.
BostonHerald  associatedpress  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Eversource Energy - Northern Pass Appeals State Siting Decision to NH Supreme Court: Developer fully committed to advancing clean energy project
Northern Pass Transmission, LLC (NPT) today (8/10) filed an appeal to the NH Supreme Court challenging a recent decision by the NH Site Evaluation Committee (SEC) denying a permit to build the proposed clean energy project. Northern Pass proponents believe that a favorable court ruling will enable the project to return to the SEC for further review in 2019.
electricenergyonline  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Northern Pass asks court to force reconsideration of transmission project | New Hampshire
Northern Pass submitted an appeal to the state Supreme Court on Friday in an effort to force a state committee to reconsider its rejection of the proposed $1.6 billion hydroelectric transmission line.
UnionLeader  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Eversource appeals Northern Pass case to NH Supreme Court
Eversource has appealed the rejection of its Northern Pass transmission line proposal to the New Hampshire Supreme Court.
wmur  associatedpress  positive  northernpass  sec  supremecourt  appeal 
august 2018 by eversourcenh
Northern Pass plans appeal to state Supreme Court | New Hampshire
Northern Pass officials plan to file an appeal with the state Supreme Court by an Aug. 13 deadline in an effort to jump-start a hydroelectric transmission project that a state committee denied.
UnionLeader  positive  northernpass  sec 
july 2018 by eversourcenh
Eversource Energy - Northern Pass Affirms Commitment to Deliver Vital Clean Energy Project to State and Region
Eversource officials remain committed to the Northern Pass project following today's final written order issued by the N.H. Site Evaluation Committee (SEC) denying the project's motion for rehearing.  The company intends to pursue all available options to bring this important project forward.   
electricenergyonline  positive  northernpass  sec 
july 2018 by eversourcenh
Committee Rejects Effort To Recuse Northern Pass Deniers | Business | caledonianrecord.com
The Site Evaluation Committee on Thursday issued a written order denying a motion seeking recusal of two members of the panel that denied Northern Pass’ application – Public Utilities Commissioner Kathryn Bailey and Public Member Patricia Weathersby.
CaledonianRecord  northernpass  sec  IBEW 
june 2018 by eversourcenh
Letter: Thank you to the SEC
Again, and again, I find myself awed, amazed and proud of the New Hampshire Site Evaluation Committee.
concordmonitor  letter  northernpass  sec  opponent 
june 2018 by eversourcenh
Sununu Signs Bill Expanding Public Member Pool, Requiring More Training For SEC | New Hampshire Public Radio
Governor Chris Sununu has signed a bill allowing him to appoint more private citizens to the state Site Evaluation Committee and requiring them to undergo more training.
nhpr  sec  training  sununu  legislation 
june 2018 by eversourcenh
Regulators Refuse Northern Pass Reconsideration; Eversource Refuses To Give Up | InDepthNH.org
State utility regulators voted 7-0 on Thursday to reject a motion to reconsider their decision turning down the $1.6 billion, 192-mile Northern Pass Transmission project.
InDepthNH  positive  northernpass  sec  appeal 
may 2018 by eversourcenh
Hydro Power Not Green Enough for New Hampshire As Regulators Reject Northern Pass Proposal – InsideSources
New England wants to go green, but, in the case of New Hampshire, only as long as doing so doesn’t effect the view or make too much noise. Last week, the New Hampshire Site Evaluation Committee (SEC) denied an appeal on behalf of Northern Pass, a 192-mile, high-voltage transmission line that would have brought Canadian hydro-power through the state to Massachusetts. The denial is the latest development in the lengthy struggle to import needed clean power to New England. However, it could be the final nail in the coffin for the project, a decision which would have serious implications for the region’s energy supply and consumer prices.
InsideSources  positive  northernpass  sec  appeal  hydropower  transmission  siting 
may 2018 by eversourcenh
N.H. panel turns aside appeal of transmission line rejection | American Public Power Association
The New Hampshire Site Evaluation Committee on May 24 rejected an appeal asking it to reconsider its decision earlier this year that denied the Northern Pass project's application for a 192-mile, $1.6 billion transmission system that would deliver lower-cost Canadian hydropower through New Hampshire and into neighboring Massachusetts.
americanpublicpower  northernpass  sec  hearing  appeal 
may 2018 by eversourcenh
Correction: Northern Pass Story | New Hampshire News | US News
In a story May 24 about a panel upholding its rejecting of the Northern Pass energy project, The Associated Press incorrectly attributed a quote about the decision. The comment came from the committee's legal counsel, attorney Michael Iacopino, not its chairman, Martin Honigberg.
usnews  ap  northernpass  sec  hearing  appeal 
may 2018 by eversourcenh
Site Evaluation Committee rejects Northern Pass appeal for new hearing | New Hampshire
There will be no reconsideration of the Northern Pass by the state’s Site Evaluation Committee.
UnionLeader  positive  northernpass  sec  appeal 
may 2018 by eversourcenh
Committee denies appeal of Northern Pass rejection
A New Hampshire committee denied an appeal Thursday on a request to reconsider its rejection of the Northern Pass transmission line proposal, and the fight might now be headed to the state Supreme Court.
wmur  positive  northernpass  sec  appeal 
may 2018 by eversourcenh
Northern Pass Poised For State Supreme Court Review, Amid New Legal Challenge | New Hampshire Public Radio
State regulators voted unanimously Thursday not to give Eversource a new hearing for its Northern Pass power line proposal.
nhpr  positive  northernpass  sec  appeal 
may 2018 by eversourcenh
N.H. panel upholds denial of Northern Pass project - The Boston Globe
N.H. panel upholds denial of Northern Pass project
A New Hampshire panel has dealt another blow to a controversial hydro project, upholding on Thursday an earlier decision to deny a proposal over concerns that it would have hurt tourism and businesses in the state. The Site Evaluation Committee unanimously voted to deny a request by Eversource to rehear the $1.6 billion, 192-mile Northern Pass transmission line project. It first voted against the project in February, which resulted in Massachusetts abandoning plans to contract with the project to fulfill its clean energy needs. — ASSOCIATED PRESS
bostonglobe  northernpass  sec  appeal 
may 2018 by eversourcenh
Northern Pass appeal rejected; Eversource considering appeal to state Supreme Court
A New Hampshire panel has dealt another blow to a controversial hydro project, upholding on Thursday an earlier decision to deny a proposal over concerns that it would have hurt tourism and businesses in the state.
concordmonitor  ap  positive  northernpass  sec  appeal 
may 2018 by eversourcenh
New Hampshire denies rehearing on Northern Pass line rejection | Utility Dive
The SEC's unanimous decision leaves Eversource with one last path to save its 192-mile transmission line: the state Supreme Court. 
utilitydive  positive  northernpass  sec  appeal 
may 2018 by eversourcenh
Tony Giunta: What does New Hampshire need? More power
Ironically, while opponents continue to cheer the New Hampshire Site Evaluation Committee’s recent decision to deny a permit to build Northern Pass – one of the largest-scale renewable energy projects ever proposed for New England – the newest movement to save the planet is quickly gaining steam (or should I say volts). Sixteen countries, including the United States (California to be more specific), have implemented bans on the internal combustion engine and over the next decade will require everyone to start driving electric vehicles.
concordmonitor  op-ed  positive  northernpass  sec  appeal 
may 2018 by eversourcenh
Opponents Want State to Deny Northern Pass a Second Chance | New Hampshire Public Radio
Opponents of the Northern Pass power project are pushing back on developer Eversource’s request for a new hearing before state regulators.
nhpr  northernpass  sec  appeal  opponents 
may 2018 by eversourcenh
Public Counsel: Northern Pass Failed To Prove Legal, Factual Errors in Project Denial | InDepthNH.org
Northern Pass fails to prove the Site Evaluation Committee made legal or factual errors in denying the utility’s transmission line application, Counsel for the Public said in opposing the project’s request to reconsider the decision.
InDepthNH  northernpass  clf  sec  motion 
may 2018 by eversourcenh
CLF Continues Fight Against Northern Pass | Conservation Law Foundation
Conservation Law Foundation (CLF) today filed an objection to Eversource’s request that the New Hampshire Site Evaluation Committee reconsider its decision to reject the Northern Pass transmission line. In the filing, CLF argues that Eversource has failed to provide good cause to reconsider the committee’s rejection of the project. The filing, submitted jointly with two other intervenors, contends that the committee’s initial decision to reject the project was correct, based on Eversource’s failure to make an honest and credible case about the impacts of the transmission line.
clf  northernpass  sec  motion 
may 2018 by eversourcenh
Municipal Groups Object To Motion Seeking Recusal of 2 Northern Pass SEC Members | InDepthNH.org
Three municipal intervenor groups in the Northern Pass project objected Monday to a motion asking that two Site Evaluation Committee members recuse themselves from further deliberations on the $1.6 billion powerline plan that was denied on Feb. 1.
InDepthNH  northernpass  sec  IBEW  businesses 
may 2018 by eversourcenh
Eversource: Filing 'Fully Addresses' Northern Pass Criticism | New Hampshire News | US News
Eversource is asking a New Hampshire panel to reconsider its rejection of the Northern Pass transmission line proposal.
usnews  ap  positive  northernpass  sec  appeal 
april 2018 by eversourcenh
Northern Pass Supporters Want Two Evaluators Removed From Appeal Hearings | New Hampshire Public Radio
Supporters of Eversource’s Northern Pass transmission line want to remove two evaluators from the appeal process for the project’s state permit.
nhpr  northernpass  sec  IBEW 
april 2018 by eversourcenh
Eversource Files Northern Pass Appeal – Again – Ahead of May Hearing | New Hampshire Public Radio
Eversource has filed a new version of its request for a new hearing on its proposed Northern Pass transmission line.
nhpr  positive  northernpass  sec  appeal 
april 2018 by eversourcenh
N. Pass officials want deliberations on transmission project reopened | New Hampshire
Northern Pass officials on Friday filed a request for a state committee to reopen its deliberations on the proposed hydroelectric transmission project that it rejected in February.
UnionLeader  northernpass  sec  appeal 
april 2018 by eversourcenh
« earlier      
per page:    204080120160

related tags

acquisition  adjudicativehearings  aesthetics  AG  AMC  americanpublicpower  antrim  ap  appeal  application  appointment  approval  Aquarion  areanewsgroup  associatedpress  balsams  BerkshireEagle  berlin  berlindailysun  berlinreporter  bethlehem  bia  BillQuinlan  bloomberg  bostonbusinessjournal  bostonglobe  BostonHerald  bow  burial  business  businesscommunity  businesses  bustour  butterfly  CaledonianRecord  canterbury  cbcnews  celltower  chamber  charliebaker  cleanenergy  CleanEnergyRFP  clf  cmp  codel  colebrook  colebrookchronicle  colebrooknewsandsentinel  column  Commonwealthmagazine  concord  concordmonitor  conservation  conservationcommission  construction  coos  cooscounty  cooscountydemocrat  costs  counselforthepublic  courthousenewsservice  ctvnews  cunningham  decision  deis  delay  delegation  deliberation  deliberations  derrynews  des  dismissed  DMo  doe  dollymcphaul  dot  e&epublishing  EagleTimes  eagletribune  earnings  easton  Economicdevelopment  economy  ecoRInews  editorial  efficiency  eis  electricenergyonline  ElectricLight&Power  Emera  EMF  energy  energycosts  energyefficiency  entergy  environment  evaluation  Eversouce  eversource  eversourceenergy  exelon  expansion  ferc  filing  finalbrief  finalbriefing  finalbriefings  finaldeliberations  financing  Forbes  forestsociety  Forrester  forwardnh  fosters  franconia  franklin  friendlycross  generation  GloucesterTimes  GreenfieldRecorder  Groton  GSPL  gtm  hartfordbusinessjournal  Hassan  hb145  HB462  hb1358  health  hearing  hearings  historicalresources  huffingtonpost  Hydro-Quebec  hydropower  hydroworld  IBEW  indepthnh  InsideSources  intervener  interveners  investors  iso-ne  jdsupra  jobs  jobsfair  johnharrigan  karner  keenesentinel  kenney  KinderMorgan  KrisPastoriza  laconiacitizen  laconiadailysun  lancaster  lapresse  lawsuit  legislation  legislators  legislature  LesOtten  letter  littlebay  Littleton  littletoncourier  londonderry  londonderrynews  londonderrytimes  lowellsun  Maggie  mainebiz  manchester  ManchesterInkLink  manufacturers  marketplace  marketwatch  massachusetts  MassLive  meeting  merrill  merrimackvalleyreliabilityproject  metering&smartenergyinternational  MonadnockLedgerTranscript  MontrealGazette  motion  MVRP  nancymartland  nashuatelegraph  nationalgrid  natureconservancy  need  NEPGA  nepr  netmeter  NewHampshire  NewHampshireJournal  newhavenregister  newington  newsbostonpost  NH1  nhbr  NHJournal  nhlabornews  nhpr  northcountry  NortheastEnergyDirectProject  NortheastUtilities  Northern  northernapss  northernpass  NPR  npt  OCA  odell  offshore  op-ed  openhouse  opinion  opponent  opponents  order  Pass  Patch  paulgrenier  permits  permitting  pessamit  pipeline  plymouth  plymouthrecord  portlandpressherald  positive  positivemulti  pressrelease  Projects  property  propertyrights  psnh  publichearings  PublicInformationSessions  publicinput  puc  rebates  regulators  rehearing  renewable  renewableenergy  RenewablesNow  reNEWS  RFP  ripr  RTOInsider  rules  saintanselmcrier  SB245  schedule  scobiepond  scrubber  seacoastonline  seacoastreliabilityproject  sealink  sec  SentinelSource  sierraclub  site  siteevaluation  SiteEvaluationCommittee  siting  smartgridnews  solar  SouthCoastToday  spnhf  sprucewind  SRP  statehousenews  study  sugarhill  sununu  support  supporter  supremecourt  T&Dworld  taxes  taxrevenue  TDI  technicalsessions  telegraph  TennesseeGasPipeline  therepublic  tourism  training  transmission  TSA  turbines  underground  Union  unionleader  upgrades  usnews  utilities  utility  utilitydive  valleynews  valuation  vose  VTdigger  washingtonpost  WBUR  wcax  wetlands  wickedlocal  wind  windfarm  wmur  writtendecision  WTSN 

Copy this bookmark:



description:


tags: